Logo

Construction Update Spring 2017

I often say that MTSU is such an exciting place to study and work due to all of the campus construction projects and improvements that are ongoing or were recently completed. Here is a brief update on those recent and current projects.

Davis Science and Wiser-Patten Science Renovations

Renovations of Wiser Patten and Davis Science Buildings.

Full renovations of Davis Science (75,500 gross square feet, constructed 1967) and Wiser- Patten (41,500 gross squarefeet, constructed 1932) are now complete. A new, central Strobel Lobby connects the two buildings and provides a direct path to the new Science Building for a new Science Corridor of Innovation comprising the three buildings—an important concept for the functional neighborhoods of the campus. ADA access was also part of the genesis of the building connector concept, with ramps leading from the central lobby up to Davis and down to two new elevators in Wiser-Patten.

Renovations of Wiser Patten and Davis Science Buildings.

Occupants of the buildings include:

•Davis Science—Geosciences, a Mechatronics Engineering lab, new Fermentation Science Lab, and new academic advising offices for the College of Basic and Applied Sciences

•Wiser-Patten—Physics and Astronomy, Anthropology, and Forensic Science

Equipment and furnishings were installed this fall, and the new and returning occupants moved in over the holiday break before the Spring 2017 semester.

Academic Building for College of Behavioral and Health Sciences

On July 14, the State Building Commission approved full planning of the proposed academic building for the College of Behavioral and Health Sciences. The SBC signed off on $1.6 million to complete the design and bid-ready documents, plus appointed Bauer Askew Architecture as designer for the project.

The building will serve the Criminal Justice Administration, Psychology, and Social Work departments, with 14 classrooms, 19 labs, 63 faculty offices, an area for advising offices, and a dean’s suite. The site is located east

of the McFarland Building and will form the beginning of a new academic quadrangle and outdoor green space north of MTSU Boulevard and the Student Union.

Middle Tennessee Boulevard Widening

Road construction on Middle Tennessee Boulevard continues to progress on schedule. The roadway was redesigned to improve traffic flow and pedestrian safety, with landscaped median and dedicated turn lanes, improved pedestrian walks and crossings, bike lanes, better lighting, additional signalized crossings at Lytle and Division, and new underground utilities. Additional enhancements to the roadway will include campus monument entry walls and signage, pedestrian and vehicular improvements to the Faulkinberry intersection, and a new drop-off drive at Murphy Center.

Utility work is progressing along the northbound lanes and is nearing completion along the southbound lanes from Lytle Street to Greenland Drive. Work will remain focused along the southbound lanes throughout the spring of 2017, when work along the northbound lanes adjacent to campus will begin. Construction completion is expected by fall of 2018.

Pedestrians are encouraged to exercise extreme caution when driving or walking in proximity to the construction zone through the course of the entire project.

Parking and Transportation Projects

The next phase of Parking and Transportation projects will focus on pedestrian walkways and lighting in the core of campus. The designs include ADA walkway improvements from the Livestock Lot; a dedicated walkway from Blue Raider Drive connecting to the south side of the Media and Honors buildings; a new sidewalk and lighting on the north side of Alumni Drive; and a widened walk on Founders Lane. A widened sidewalk and additional lighting are planned from Business and Aerospace to the north side of KUC, with intersec- tion improvements at Champion Way and Military Memorial. In addition, the Murphy Center lot will undergo resur- facing, along with new lighting and ADA parking improvements. The project is expected to bid in the spring, with construction beginning early summer.

Saunders Fine Arts HVAC Update

The second and final phase of the Saunders project consists of the removal of all window air conditioning units, replacement of the window systems in the building, and completion of the connection of the Saunders building to the campus central heat and cooling system. The work is planned to begin in early summer and to reach substantial completion by mid-August 2017.

 

Construction Update

MTSU is an exciting place to work and study in large part because so many improvements are underway! Here are some highlights of recent and current projects.

Science Building

Construction on MTSU’s new $147 million Science Building began in May 2012. Construction is on  schedule, an a steel topping-out ceremony took place Jan. 11. The project will result in approximately 257,000 gross square feet for biology and chemistry, 37 class labs, two open labs, 13 research labs, six classrooms, faculty offices, numerous informal learning areas, and space for student presentations. Approximately 1,500 new student stations will be provided in the labs and classrooms. The building will accommodate state-of-the-art teaching and research technologies. The design features best practices in sustainability by meeting Tennessee State Sustainability Guidelines, and the completed facility will be the equivalent of LEED-certified. The project is planned to be ready for move-in by fall 2014 and ready for classes in spring 2015.

Student Services Building and Parking Garages

Construction began last spring for a new Student Services Building located east of the new Student Union and adjacent to the Campus Recreation Building. The Student Services Building will relocate all functions related to Admissions, Records and Enrollment, Financial Aid, Scheduling, the Bursar’s Office, and Academic Advising. The facility will serve as a starting point for campus tours and as the primary visitors’ center for prospective students and their families. The building will include a bridge from a new student parking garage, through the Student Services Building and extending across Blue Raider Drive to the second-floor ballroom level of the new Student Union. Construction and move-in are expected to be complete by the start of fall semester 2014.

LRC Renovation

Renovation of the Learning Resources Center began Dec. 2011, and construction is now substantially  complete and ready for classes. The project accommodates the Interior Design and Textiles, Merchandising, and Design programs in the academic campus core. Creative and Visual Services has moved into newly renovated space in the Fairview Building, and WMOT and WMTS are now in the new Center for Innovation in Media in the Bragg Mass Communication Building.

Parking

Current parking projects include construction of two new student parking garages. One is adjacent to the Health, Wellness, and Recreation Center, and the other is in the Holmes Building lot close to Greenland Drive. The garages will give students convenient access from the edge of campus and direct pedestrian traffic to the core of campus. Each will have approximately 490 spaces for students and will be  substantially complete in summer 2013.

Transportation

The next phase of roadway improvements includes the widening of Lightning Way and the widening of Champion Way with a new turn lane at Greenland Drive; a new rotary at the intersection of those two roads; and improved pedestrian walkways, crosswalks, and lighting. Construction is expected to begin spring 2013 with substantial completion of the new rotary in the summer of 2013 and completion of the overall project by summer 2014. All roadway projects are designed to improve shuttle bus efficiency and traffic flow, relieve traffic congestion, improve pedestrian walkways and lighting, and provide bike lanes into campus and around the perimeter of the academic core.

Underground Electric Work

Construction of underground electrical duct banks is nearing completion, in what will be an electrical loop around campus. This project will improve electrical service capacity and reliability while enhancing the campus by removing most overhead lines, which will be removed following temporary, required power outages.

Campus Construction Update

MTSU is an exciting place to work and study in large part because so many renovations and new buildings are underway, taking shape, or opening for use! Here are some highlights of recent and current projects.

MTSU Jeff Hendrix Stadium Club Ribbon Cutting

Dedication and ribbon cutting ceremony of the Jeff Hendrix Stadium club in MTSU’s Floyd Stadium made possible by a $1 million donation by Jeff Hendrix estate.

Jeff Hendrix Stadium Club: Located between the 30-yard lines of Floyd Stadium, the new club features a climate-controlled lounge and more than 550 outdoor chair-back seats. The project, which was formally dedicated on Aug. 20, is a result of a $1 million private donation from the estate of long-time MTSU supporter Jeff Hendrix.

Learning Resource Center (LRC) Renovation: This $7.2 million renovation project in the heart of campus will provide new offices, classrooms, and labs for the College of Behavioral and Health Sciences, primarily the Department of Human Sciences. The building will reopen in January 2013. (LRC 221 is scheduled to open in spring 2013.)

Parking Garages: Two parking structures (one near the Holmes Building and one near the as-yet-unbuilt Student Services Building) are under construction.

They will provide 990 parking spaces (a net gain of 887). A second-level bridge will connect the Student Services garage to and through Student

Services, over Blue Raider Drive, and into the Student Union at the ballroom level. The total cost of the garages is $23.5 million.

Student Services Building: Located next to the MTSU Student Union, this $16 million building is to be occupied in fall 2014. It will be a one-stop area for students to conduct University business (Admissions, Financial Aid, Advising, and Bursar’s Office).

Science Building: The 250,000-square-foot structure, next to Walker Library, will house 36 teaching labs; four classrooms (150-, 75-, 60-, and 50-seat); 12 research suites (physiology, organismal, molecular, synthetic, analytical); 85 offices; one research space for integrated life sciences; one research space for computation; a greenhouse; a vivarium; graduate student spaces; and informal learning spaces. The total project cost is $147 million.

Conference Center: Designed as a flexible meeting, seminar, or special event venue (with a seating capacity of 32 for a seminar, 96 for dining, and 160 for lectures), this $1 million project is scheduled for completion in fall 2013.

Widening and Improvements to Middle Tennessee Boulevard: Bike lanes, wider lanes, a landscaped median, and traffic-calming features for pedestrian safety at intersections.

Ongoing Parking and Transportation Enhancements: The new entrance and signal at Greenland Drive and Blue Raider Drive is open and fully operational. Improvements along MTSU Boulevard through the core of campus have improved shuttle bus efficiency and pedestrian safety. Sidewalks have been widened, and ADA access has been improved. The new rotary supports efficient traffic flow at the new intersection at Blue Raider Drive and Lightning Way. The next phase of construction in this area is in design and slated to start this fall. Turn lanes at Champion Way will be widened; Lightning Way will be widened to accommodate shuttle buses and bike lanes; and the addition of a new rotary at the intersection of Lightning Way and Champion Way will improve traffic flow into and out of campus.

Campus Lighting Enhancements: Phase 1, in which we retrofitted and replaced existing lights with newer-technology fixtures and converted high pressure sodium lamps to metal halide, is complete. Nighttime visibility and general campus illumination has been improved for better security. The replacement fixtures use roof-mounted optics and “dark sky” features consistent with recommended best practices in energy and environmental design and corresponding State

of Tennessee Sustainable Design Guidelines. Phase 2, still to come, will add new light fixtures to improve lighting consistency for better visibility and improved security.

Keathley University Center Renovation: This $2.3 million project will include the development of a new facility in the former Phillips Bookstore space to consolidate testing centers and also improve the Post Office space. It will accommodate Disabled Student Services testing, University Studies assessments, University College Distance Learning for online courses and correspondence exams, and Testing Services (licensure, certifications, ACT, GRE, LSAT, senior major field tests, etc.).

ADA Renovations and Elevator at Alumni Memorial Gym: This project provided full accessibility to the gym level and classes on the lower floor.

Women’s Practice Soccer Field: A new practice field at the corner of Greenland and Blue Raider Drive will replace the former field adjacent to the women’s softball field (The old field will become a parking lot.) The new field will be completed this summer and ready for play in late fall 2012.

Concrete Industry Building: This $11.2 million proposed building is in the design phase.

Student Housing: House #4 on Greek Row has been renovated and is scheduled to open in August under Housing management and will be occupied by Chi Omega. They join the Global Learning Community, which will continue to occupy House #7. Two more houses, #2 and #6, will be renovated during the 2012–2013 academic year and turned over to Housing for occupancy during 2013–2014.

Secured By miniOrange